Project status
Completed
Location
Farley, NSW
Client
ARTC
Start Date
Mar 2014
Completion Date
May 2014

ARTC engaged Martinus to undertake these critical infrastructure works within the
Hunter Valley corridor as it is nearing the end of its serviceable life.

Project scope involved:
• Removal of existing turnout
• Track formation and reconditioning works
• Removal and reinstalment of signalling infrastructure
• Relocation and installation of new R300:12 spring wing turnout
• All associated commissioning works

These works have been completed safely and on time within a major 62 hour track closedown.

Martinus has gained industry acknowledgment for its expertise in track construction possession works.