Project status
In-progress
Location
Regional Queensland
Client
Adani Australia
Start Date
Feb 2020
Completion Date
Sep 2021

Martinus has commenced construction on the $230 million North civil package for the Carmichael Rail Network.

The scope of works includes, construction of 86-kilometres of rail formation works, 10 new multi-span bridges and the installation of over 40km of culverts.

The project will peak with more than 100 staff and 600 blue collar workers. The project team has mobilised to site and is currently on schedule to deliver this major, complex rail project. This project is being delivered under Martinus self delivery model utilising local plant hire companies and our internal blue collar work force.

This project is one of the most logistically complex and environmentally sensitive projects currently being delivered in Australia. The Martinus team worked collaboratively with the Adani team through an early works agreement to optimise and innovate the design and construction methodologies, this has resulted in an improved design and construction program.

The project is exceeding the social sustainability targets, with 9% indigenous employment, 100% of employment from the greater QLD region and more than $70M of spend going to the local regions and communities.

10 large multi-span waterway and road bridges
500+ employee’s and contractors
3 million cubic metres of earthworks